Connections photograph

Connections

Use attributes for filter !
First episode dateOctober 17, 1978
Final episode dateDecember 19, 1978
Presented by James Burke
Creators James Burke
Networks BBC
BBC One
Date of Reg.
Date of Upd.
ID2314074
Send edit request

About Connections


An interdisciplinary approach to the history of science and invention.

Renewable energy projects worth billions stuck on hold

Renewable energy projects worth billions stuck on hold
May 10,2023 10:01 pm

... Energy companies like Octopus Energy, one of Europe s largest investors in renewable energy, say they have been told by National Grid that they need to wait up to 15 years for some Connections - far beyond the government s 2035 target...

Many Android phones to get satellite connectivity

Many Android phones to get satellite connectivity
Jan 5,2023 6:21 pm

... Satellite broadband is fast and generally reliable, but more expensive than cable or fibre Connections...

Bolsover: The small town with dreams of becoming a city

Bolsover: The small town with dreams of becoming a city
Feb 27,2022 3:54 am

... " We have got royal Connections - Charles I and Queen Henrietta Maria were entertained at Bolsover Castle in the 17th Century - and Bess of Hardwick was one of the most notable figures of Elizabethan English society...

Chileans divided ahead of presidential run-off

Chileans divided ahead of presidential run-off
Dec 19,2021 3:19 am

... In turn Mr Boric, a former student protester, has played on his rival s authoritarian Connections - Mr Kast s father was recently revealed to have been a member of the Nazi party...

Paul Whelan: The curious case of ex-marine in prison for spying in Russia

Paul Whelan: The curious case of ex-marine in prison for spying in Russia
Jun 24,2020 10:24 am

......

Digital poverty in the schools, in which a few laptops

Digital poverty in the schools, in which a few laptops
Apr 24,2020 2:42 am

... their families may have cell phones with internet Connections - but for those, the data is in low-paid, insecure jobs, expensive...

Gare du Nord: Why Europe's busiest station needs a makeover fast

Gare du Nord: Why Europe's busiest station needs a makeover fast
Feb 16,2020 9:34 am

... They also know that as Europe s busiest station - serving local, regional and international Connections - the Gare du Nord acts as a window to the capital...

General election 2019: Who are the voters that can't make up their minds?

General election 2019: Who are the voters that can't make up their minds?
Feb 16,2020 8:50 am

... There also is strong evidence voters prefer candidates with local Connections - research has even indicated the distance between a voter s home and the candidate s residential address is a predictor of their level of support...

Renewable energy projects worth billions stuck on hold

Feb 16,2020 5:58 am

By Esme Stallard & Justin RowlattBBC News Climate and Science

Billions of pounds' worth of green energy projects are on hold because they cannot plug into the UK's electricity System , BBC research shows.

Some new solar and wind sites are waiting up to 10 to 15 years to be connected because of a lack of capacity in The System - known as the " grid".

Renewable Energy companies worry it could threaten UK climate targets.

National Grid, which manages The System , acknowledges The Problem but says fundamental reform is needed.

The UK currently has a 2035 target for 100% of its electricity to be produced without carbon emissions.

Last Year net-zero.

But meeting The Target will require a big increase in The Number of renewable projects across the country. It is estimated as much As Is needed.

The government and private investors have spent £198bn on renewable power infrastructure since 2010. But now energy companies are warning that significant delays to connect their green energy projects to The System will threaten their ability to bring more green power online.

A new wind farm or solar site can only start supplying energy to people's homes once it has been plugged into The Grid .

Energy companies like Octopus Energy , one of Europe's largest investors in Renewable Energy , say they have been told by National Grid that they need to wait up to 15 years for some Connections - Far beyond the government's 2035 target.

'Longest grid queues in Europe'

There are currently More Than £200bn worth of projects sitting in the Connections queue, The Bbc has calculated.

Around 40% of them face a connection wait of at least a year, according to National Grid's own figures. That represents delayed investments worth tens of billions of pounds.

" We currently have one of the longest grid queues in Europe, " according to Zoisa North-Bond, CEO of Octopus Energy Generation.

The Problem is so many new renewable projects are applying for Connections , The Grid cannot keep up.

The System was built when just a few fossil fuel power plants were requesting a connection each year, but now there are 1,100 projects in the queue.

Torbay Council has been hit by the delays. The diggers are already clearing the ground for a 6-hectare solar plant it is building in Torquay. It is due to be finished next year.

The Council plans to use money raised from selling the energy to help fund local services, but it has been told The Plant will not be connected for five years.

And even that date isn't certain. " Worryingly, there are some indications that that could slip into the mid 2030s" said Alan Denby from Torbay Council. " That's a real problem for The Council in that we declared that we wanted to be carbon neutral by 2030. "

With projects unable to get Connections , construction is either being paused or projects are being completed but are unable to produce any power.

National Grid, which is responsible for moving electricity across England and Wales, says it is tightening up the criteria for projects to apply so only the really promising ones join the queue.

But a huge new investment is also required to restructure The Grid so it can deal with more power sources, says Roisin Quinn, director of customer Connections .

" Fundamental reform is needed" she told The Bbc . " More infrastructure is needed. We Are working very hard to design and build at a faster pace than we ever have done before. "

The Energy Network Association represents the operators, known as DNOs, which connect people's homes to the main System owned by National Grid. It says that the government needs to speed up the planning process so electricity infrastructure can be built more quickly.

The government that it was looking into How To speed up planning decisions.

The energy regulator, Ofgem, which oversees the operators, said that all stakeholders were playing catch up with the government's targets.

Rebecca Barnett, direct of networks at Ofgem said: " The targets have been increasing in The Last two or three years dramatically and there is a long lead in investment time that is needed to commit, develop, and deliver these really big assets.

" I think that has caused a real problem; we definitely need to catch up. The incremental approach of The Past is not fit for purpose. "

Ofgem says it has agreed to allow The National Grid to raise an additional £20bn over The Next 40 Years from customer bills to pay for the huge upgrades The Grid needs.

Customers have seen household prices soar over the Last Year following.

But Ms Barnett said this new investment will have a minimal impact on customers bills and will help shoulder The Burden of some of the volatile energy prices.

" The Future is for green, more secure and in fact cheaper energy. We know there is some investment cost needed to get us there, but in the Long Run it is going to be cheaper for us all, " She Said .

Related Topics

Source of news: bbc.com

Related Persons

Next Profile ❯